Project Timeline

The committee, along with Silver/Petrucelli and Gilbane, has been working very closely with the Superintendent, Dr. Schumann, and other educators to create a timeline for construction. Below is a high level timeline the committee is working towards. This is a work in progress as adjustments may need to be made to accommodate for any issues that arise during construction.

 

  • Ground Breaking - May, 2014

  • Enrico Fermi STEAM Wing - June, 2014 through November, 2015 - Complete
  • Cafeteria / Health Addition - October, 2014 through November, 2015 - Complete
  • Kitchen / Renovate Existing Cafeteria - March 2015 through November, 2015 - Complete
  • Renovate Gymnasium and Locker Rooms - June, 2015 through April, 2016 - Complete
  • Occupation of Enrico Fermi STEAM Wing - November, 2015
  • Abate and Demolition of Existing D Wing - December, 2015 through March, 2016 - Complete
  • Lobby Addition - December 2015 through July, 2016 - In Progress
  • Renovation of Existing A and B Wings - October, 2015 through July, 2016 - In Progress
  • Music Addition - November, 2015 through January, 2017 - In Progress
  • Renovate and Complete Auditorium - December, 2015 through January 2017 - In Progress
  • Site Parking - June, 2016 through August, 2016