SPECIAL MEETING NOTICE OF ACTION


ENFIELD INLAND WETLANDS AND WATERCOURSES AGENCY
TUESDAY, AUGUST 1, 2006
7:00 P.M.
*****ENFIELD ROOM*****
*********LOWER LEVEL, ENFIELD TOWN HALL *********
*** 820 ENFIELD STREET,***
** ENFIELD, CT 06082 **

SPECIAL MEETING

1. Call to Order The Special Meeting was called to order by Chairperson Pfeifer-Hall at 7:00 p.m.

2. Roll Call: Present were: Chairperson Gretchen Pfeifer-Hall and Agents Arnone, Poirot, Staples, Szewczak and Wawer. Also present were Neil Angus, Wetlands Agent and Susan Berube, Recording Secretary.


3. Approval of Minutes -- July 18, 2006 Meeting: A motion was made by Agent Szewczak and seconded by Agent Arnone to approve the minutes of the meeting of July 18, 2006 with the following corrections: First page, in both “Members Present” heading and #2, Roll Call, change Agent Wawer’s time of arrival to 7:30 p.m., page 5, third paragraph, change “that” to “than”. Vote was 6-0-0.

4. Business

IW#460 - Stonegate Associates - Proposed 76-Unit Senior Residential Development involving excavation, filling regrading and placement of structures in and within 100 feet of wetlands and watercourses. Property located off of Mayfield Drive, West View Drive, Pine Hill Road and West Shore Drive (Map 79 Lots 11, 12, 13 and Map 96 Lot 11) Zoned R-44 [Submitted March 29, 2006; Received April 4, 2006; PPE April 18, 2006; EMPHCD July 18, 2006; MPHAD August 22, 2006] After lengthy discussion, a motion was made by Agent Poirot and seconded by Agent Wawer to approve IW#460 with the 10 standard conditions, in addition to the following 19 as amended during discussion:

11. Units #14, 16 and 18 are to be eliminated, modifying the total number of units from 76 to 73, as shown on the site plan entitled "Overall Layout Stonegate, Prepared for Stonegate Associates, Enfield, Connecticut"; dated 2-14-06; revised through 7-17-06; Sheet 2 of 33; Prepared by Wentworth Civil Engineers, LLC, 177 West Town Street, Lebanon, CT 06249 (Exhibit #59). All required approved plan sheets, including but not limited to sheets 2, 7-10, 12, 19-22, 24, 26-29, shall be revised to reflect this reduction in units and change in locations of basins and phasing lines, prior to filing of the mylars;

12. Those portions of the total site indicated to be conservation easement shall be first offered to the town as an easement or restrictive covenant. The Easement language shall be approved by the Town Attorney and filed prior to the issuance of the first Certificate of Occupancy. Conservation easement markers shall be installed in accordance with Town requirements, by a licensed surveyor, at the applicant's expense. Easement markers will be provided by the Planning Department. Where no trees are present greater than 6" dbh, easement markers shall be placed on 4"x4" wooden posts to demarcate the easement boundary. Should the Town Council decline the acceptance of the easement or restrictive covenant, a notification shall be placed on the land records that indicates the extent of wetland and watercourse resources on-site and the regulations governing those resources, including the prohibition of live vegetation removal and disposal of refuse and/or yard waste within 100 feet of wetlands and watercourses.

13. This project is approved in five (5) phases as shown on the approved plan set. Fore each phase, the base course of asphalt must be installed and all exposed areas surrounding the unit are temporarily or permanently stabilized prior to the Wetlands Agent signing off on any certificates of occupancy. Should stabilization not be possible due to the time of year, a stabilization bond will be required to be posted by the owner in the amount of $500 for each unit prior to the Wetlands Agent signing off on the Certificate of Occupancy. Phasing plan narrative on Sheet 30 of 33 shall also be amended to eliminate the construction of 2 model homes in phase 3;

14. Limits of disturbance for each phase are to be clearly marked in the field in accordance with the approved plans and approved by the Wetlands Agent prior to the commencement of any vegetation removal. Construction fencing shall be used to identify the limits of disturbance adjacent to approved crossing areas;

15. For each phase, all perimeter and approved crossing erosion and sediment controls and construction fencing must be in place prior to the Wetlands Agent signing off on any building permits;

16. In-stream and in-wetland construction activities associated with the approved crossings shall take place only during low flow conditions (July 1 through September 30) to minimize excessive erosion and sedimentation as a result of excessive runoff and heavily saturated soils. Any dewatering required shall occur within the approved limits of disturbance and not be directly discharged into wetlands or watercourses. Where diverted runoff is expected to be carrying a sediment load, the runoff shall be released to a sediment impoundment prior to discharge to wetlands or watercourses. Construction access to the east side of the Stonegate Drive crossing at Sta.11+75 shall be from the existing crossing at Sta.37+40 (Westgate Drive). No construction equipment is permitted to cross through the wetland areas unless otherwise indicated on the approved plans;

17. Wetland Creation plans are approved in accordance with the May 11, 2006 Report from REMA Ecological Services (Exhibit 24). Referenced plans: Sheet M-1 and M-2 entitled "Landscaping Plan for Proposed Wetland Mitigation Showing Approximate Locations for Proposed Plants and Seeding Areas Wetland creation"; dated May 11, 2006. Westgate Drive wetland mitigation is approved in accordance with the details listed in the June 6, 2006 report from REMA (Exhibit 45) including mitigation area details, including planting notes, installation, follow-up maintenance and monitoring and planting materials lists;

18. A 'Wetland Enhancement Bond' shall be posted for both created wetlands, all detention basins, infiltration basins and buffer/crossing enhancement plantings. Bonding shall be calculated using the cost of plantings, plus a 50% mark-up for installation and labor. The bond amount is to be set by the Wetlands Agent and the full amount posted prior to the issuance of any building permits. Bonding is permitted to be phased in accordance with the approved phasing plans (for the purposes of bonding, the wetland creation area in the utility ROW is part of Phase I). Timing of release of the bond is after two full growing seasons and submittal of the second Annual Monitoring Report as required on sheet M-2 of the Wetland Mitigation Plan submitted by REMA(Exhibit 24). Should the report identify problematic conditions, the bonding will be held for an additional year, or until a favorable report is submitted by the Wetland Scientist;

19. At the applicant's expense, a Wetland Scientist must be hired to oversee each approved crossing construction (including temporary diversion construction and maintenance) and temporary and permanent stabilization in accordance with the 2002 CT Guidelines for Soil Erosion and Sediment Control. The Wetland Scientist must also oversee the construction of both wetland creation areas and all detention and infiltration basins, as well as all associated mitigative plantings, in accordance with the approved plans and reports. Upon the completion of each crossing and wetland mitigation area, the Wetland Scientist shall submit a report to the Agency to verify completion in accordance with the approved plans;

20. A Baseline Water Quality Monitoring Plan and Construction Water Quality Monitoring Plan are required to be implemented as part of this development as detailed in the May 11, 2006 REMA report (Exhibit #24). In the event of any problems identified, the applicant will implement the necessary controls as recommended by the consultant and/or Town Staff. Interim monitoring reports are to be submitted to the Agency as required;

21. Post-construction surface water quality monitoring plan entitled "Management Plan for Stonegate Estates, Mayfield Drive, Enfield, CT", dated March 2006, prepared by Somerset Development, LLC, Enfield Connecticut, as detailed in Appendix 2 of the REMA Report dated March 29, 2006 (Exhibit #5), is to be incorporated into the management plan documents transferred from the developers to the entity assuming ownership of the common properties. A copy of the document must be provided to the Enfield Department of Planning before the Wetlands Agent may sign off on the first building permit;

22. The report entitled "Landscaping and Integrated Pest Management (IPM) Plan to Minimize Environmental Impacts" dated May 2006 as detailed in the May 11, 2006 REMA report (Exhibit #24) is to be incorporated into the management plan documents transferred from the developers to the entity assuming ownership of the common properties. A copy of the document must be provided to the Enfield Department of Planning before the Wetlands Agent may sign off on the first building permit;

23. The Stormwater Runoff Management Plan on Sheet 33 of 33 is to be followed for long-term maintenance. The following notes shall be added to the appropriate section of the plan: "Supplemental wetland plantings shall be installed if significant portions have not established or after sediment accumulation removal and/or filter berm replacement." and "Any dewatering required for basin maintenance shall not be directly discharged to wetlands and watercourses" and "The responsible party shall maintain up-to date inspection logs and maintenance reports. Failure to follow the approved Plan will result in a violation of this permit and be subject to enforcement action as per the Enfield Inland Wetlands and Watercourses regulations". This plan is to be incorporated into the management plan documents transferred from the developers to the entity assuming ownership of the common properties. A copy of the document must be provided to the Enfield Department of Planning before the Wetlands Agent may sign off on the first building permit ;

24. Permeability tests shall be conducted to confirm the final permeability rates of the constructed infiltration basins to ensure rates are within the acceptable range of ½ " to 5" per hour. The ideal rate is 2" per hour;

25. The revised "typical infiltration basin detail" submitted on July 18, 2006 (Exhibit #61) shall replace the current detail on Sheet 31 of 33. This change shall be added to the final approved plans prior to filing of the mylars;

26. All sedimentation structures (CB3, 17, 29, 39, 46, 53) are to be replaced with hydrodynamic separators. Hydrodynamic structures must be appropriately sized to adequately treat the "first flush" and avoid re-suspension of materials. Sizing calculations must be submitted and approved by the Town Engineer. Quarterly detailed maintenance schedules, as per the manufacturers specifications, must be added to the stormwater management plan on sheet 33 of 33 and incorporated into the management plan documents transferred from the developers to the entity assuming ownership of the common properties);

27. The following note is to be added to the Rain Garden Notes and Specifications on Sheet 23 of 33, as per REMA's June 6, 2006 report (Exhibit 45): "12. Raingarden area will be approximately 333 square feet. Plant 14 shrubs in each raingarden: three (3) each of two of the medium-tall shrub species and eight (8) low meadowsweet shrubs, in single species groupings (species listed above)." Rain Gardens depicted on Sheets 18-22 of 33 must be installed by a qualified professional, in accordance with the specifications and notes on sheet 23 of 33. Minor modifications/variations in locations are permitted within the approved limits of disturbance, based on site conditions. Additional rain gardens and/or dry wells may also be constructed within the approved limits of disturbance if soil and site conditions warrant;

28. Any fill material brought into the site must be inspected by a qualified individual to ensure it is relatively free of invasive seeds and/or plants;

29. With the exception of the additional items stated in these conditions, this application is approved in accordance with the Site Plans entitled "Stonegate Estates Prepared for Stonegate Associates, Enfield, CT, 76 Unit Senior Residential Development" Sheets 1 through 17 and 24 through 33, dated 2-14-06, revised through 7-17-06; prepared by Aeschliman Land Surveying, PC, 1379 Main Street, East Hartford, CT 06108 and Wentworth Civil Engineers, LLC, 177 West Town Street, Lebanon, CT 06249; and Landscape Plans entitled "Landscape Plan Stonegate, Prepared for Stonegate Associates, Enfield, Connecticut" Sheets 18 through 23, dated 2-14-06 and 9-9-05, revised through 5-26-06; prepared by Raymond Jefferson Landscape Architect, 790 Farmington Ave, Farmington, CT 06032. Any changes that would potentially cause greater impact to wetlands or watercourses, such as enlargement or reorientation of structure footprints, from the plans and any denial or changes made by any other regulatory agency or commission shall require the permittee to come before the Enfield Inland Wetlands and Watercourses Agency for a Permit Modification or Determination of Permit Need (Jurisdictional Ruling).

Vote was 4-1(Staples)-1(Szewczak). Reason for approval was that the project, with mitigation, will not adversely affect wetlands and watercourses.

• Next regular meeting is Tuesday, September 5, 2006 at 7:30PM in the Enfield Room

5. Adjourn: A motion was made by Agent Arnone and seconded by Agent Wawer to adjourn the meeting at 8:50 p.m. Vote was 6-0-0.


Acronym Key for Dates:
Submitted = Day it was Logged in by the Appropriate Town Office.
Rec’ed = Received (Date of First Regular Meeting after the day of submission or 35 days, which ever is sooner)
PPE = Petition Period Ends (14 Days from Receipt)
MAD = Mandatory Action Date (65 Days from Receipt)
EMAD = Extended Mandatory Action Date (Any combination up to 65 days from original MAD)
MPHCD = Mandatory Public Hearing Closing Date (35 Days from opening of the public hearing)
EMPHCD = Extended Mandatory Public Hearing Closing Date (Any combination up to 65 Days from first MPHCD)
MPHAD = Mandatory Public Hearing Action Date (35 Days after close of the public hearing)
EMPHAD = Extended Mandatory Public Hearing Action Date (Any combination up to 65 Days from first MPHAD)
*Applicant can consent to extend the time frame for any of the steps but the total of all extensions together cannot exceed 65 days

Last Modified: 9/8/2006 3:26:51 PM