- Home
- Departments
- Public Works
- Engineering
- Construction Project Updates
Current ROADS 2021 Construction Projects
- River - Washington
- ROADS 2021 - Year 1
- ROADS 2021 - Year 2 - Abbe Road
- ROADS 2021 - Year 2 - Meadowlark Area
- ROADS 2021 - Year 3 - Thompsonville 2024
- ROADS 2021 - Year 3 - Hazardville West
- ROADS 2021 - Year 3 - Enfield Southwest
- Powder Hollow Baseball Field Improvements
- Higgins Park Parking Lot
- Elm Street Sidewalk Gap Community Connectivity Grant
- Town Farm Road Multi-Use Path LOTCIP
- Crack Seal Program 2023
- South River Street Bridge Replacement
- Orlando Drive Culvert
- Freshwater Pond Forebay Dredging
- 45 Kimberly Drive Drainage Outlet Design
- Brainerd Park Softball Proposed Field
- Palomba Drive Bridge Funding Application
- Sinkhole at 57 South Road
River - Washington
Contact: John Cabibbo, P.E. - Assistant Town Engineer (jcabibbo@enfield.org)
Street: South River Street, Washington Avenue
Designer: Milone & MacBroom
Inspector: BETA
Contractor: Spazzarini
Project Update
This project is complete.
Roads 2021 - Year 1
Contact: J.P. Rodriguez – ROADS Engineer (jrodriguez@enfield.org)
Streets: Cheryl Drive, Cranbrook Blvd, Edmund Lane, Moody Road (Elm Street to North Maple Street), Stephen Drive
Designer: VHB
Inspector: BETA Group
Contractor: Hinckley Construction
Project Update
Road work on Cheryl, Edmund, Stephen and Moody Road have been substantially completed. Hinckley Construction is still working on turf and driveway restoration on these four streets. Work has commenced on Cranbrook Blvd. Notices were mailed and hand delivered to the businesses on Cranbrook Blvd., prior to the start of work.
Notice of Start of construction to Cheryl Drive, Edmund Lane and Stephen Drive, April 14, 2023 (PDF)
Edmund, Cheryl & Stephen Watermain Delay
Roads 2021 - Year 2 - Abbe Road
Contact: J.P. Rodriguez – ROADS Engineer (jrodriguez@enfield.org)
Streets: Abbe Road from Route 191 to Powder Hollow Road
Designer: Weston & Sampson
Inspector: Beta Group Inc
Contractor: Spazzarini Construction
Project Update
Road work on Abbe Road from Monroe Road to Coolidge Drive has been substantially completed. Spazzarini Construction is still working on turf and driveway restoration in that section. Work on Abbe Road, from Coolidge Drive to Broadbrook Road, continues including drainage improvements and shifting of the road.
Abbe Road Informational Meeting
Roads 2021 - Year 2 - Meadowlark Area
Contact: J.P. Rodriguez – ROADS Engineer (jrodriguez@enfield.org)
Streets: Broadleaf Lane, Hillyer Drive, Meadowlark Road, Pearl Street Extension, Storrs Road, Trinity Drive, Yale Court and Yale Drive
Designer: Weston & Sampson
Inspector: TBD
Contractor: TBD
Project Update
Contractor is getting the construction bonds; the construction contract should be signed late next week.
Roads 2021 - Year 3 - Thompsonville 2024
Contact: J.P. Rodriguez – ROADS Engineer (jrodriguez@enfield.org)
Streets: Garfield Street, Grant Street, Harrison Avenue, High Street (Pearl St to Prospect Street), McConn Avenue, Oak Avenue, Sullivan Avenue, Summer Street and Walnut Street
Designer: BETA GROUP
Inspector: TBD
Contractor: TBD
Project Update:
BETA Group Inc. has been awarded the engineering design of the Thompsonville 2024 Project. Topographic survey has been completed; geotechnical report is under way as well as 25% engineering design.
Roads 2021 - Year 3 - Hazardville West
Streets: Arbor Road, Powder Ridge Road and Webster Road
Designer: VHB
Inspector: TBD
Contractor: TBD
Project Update:
Field survey is complete. 25% preliminary design has been submitted to Engineering for review/comments.
Roads 2021 - Year 3 - Enfield Southwest
Contact: J.P. Rodriguez – ROADS Engineer (jrodriguez@enfield.org)
Streets: Ann Street, Middlesex Drive, Prior Road, Putnam Drive, Quaker Lane (Bass Drive to Colonial Road) and Roseanne Street
Designer: VHB
Inspector: TBD
Contractor: TBD
Project Update:
Field survey is complete. 25% preliminary design work underway.
Powder Hollow Baseball Field Improvements
Contact: J.P. Rodriguez – ROADS Engineer (jrodriguez@enfield.org)
Designer: SLR
Inspector: TBD
Contractor: TBD
Project Update
Consultant submitted the stamped/signed construction plans, project manual has been approved to go to bid, wage rates has been requested to the State.
Higgins Park Parking Lot
Contact: J.P. Rodriguez – ROADS Engineer (jrodriguez@enfield.org)
Designer
SLR
Inspector: TBD
Contractor: TBD
Project Update:
Bid opening was August 10, 2023. Four Seasons Landscaping is the low bidder.
Elm Street Sidewalk Gap Community Connectivity Grant
Contact: J.P. Rodriguez – ROADS Engineer (jrodriguez@enfield.org)
Designer: VHB
Inspector: TBD
Contractor: TBD
Project Update:
Eversource completed the pole relocation work, the other utilities’ wires relocation work is ongoing. Construction plan-set reviewed by CTDOT. Project Manual was approved by Finance & Legal Departments. Waiting on final approval from CTDOT to go out to bid.
Town Farm Road Multi-Use Path LOTCIP
Contact: J.P. Rodriguez – ROADS Engineer (jrodriguez@enfield.org)
Designer: AECOM
Inspector: TBD
Contractor: TBD
Project Update:
IWWA has been approved. The project design is at almost 100% completion. Waiting on CTDOT to complete the ROW acquisitions.
Crack Seal Program 2023
Contact: J.P. Rodriguez – ROADS Engineer (jrodriguez@enfield.org)
Designer: Town
Inspector: Town
Contractor: TBD
Project Update:
A Street list has been compiled, reviewed, and approved by DPW and Highway. Connecticut Sealcoating LLC has been scheduled to do this work through a State contract. The work is scheduled for Fall 2023.
South River Street Bridge Replacement
Contact: John Cabibbo, P.E. - Assistant Town Engineer (jcabibbo@enfield.org)
Designer: GM2 Associates
Inspector: GM2 Associates
Contractor: ROTHA Contracting Company of Avon CT
Project Update:
The bridge is closed to traffic. The bridge beams have been installed. The contractor is working on the bridge deck and bridge approaches.
Orlando Drive Culvert
Contact: John Cabibbo, P.E. - Assistant Town Engineer (jcabibbo@enfield.org)
Designer: GM2 Associates
Inspector: GM2 Associates
Contractor: Dayton Construction Company of Watertown, CT
Project Update:
The project is complete.
Freshwaster Pond Forebay Dredging
Contact: John Cabibbo, P.E. - Assistant Town Engineer (jcabibbo@enfield.org)
Designer: Weston & Sampson
Inspector: TBD
Contractor: TBD
Project Update:
Freshwater Pond Forebay Dredging design has completed survey of the forebay and analysis of the sediment. Due to extensive permitting requirements, forebay dredging is scheduled to start in 2024. Working on sediment disposal options, based on the chemical sediment analysis.
45 Kimberly Drive Drainage Outlet Design
Contact: John Cabibbo, P.E. - Assistant Town Engineer (jcabibbo@enfield.org)
Designer: Wright-Pierce
Inspector: TBD
Contractor: TBD
Project Update:
Requested funds for construction moved to next fiscal year under the CIP budget. Working with consultant on easement map, for easement acquisition.
Brainerd Park Softball Proposed Field
Palomba Drive Bridge Funding Application
SLR completed the required bridge inspection and report and completed the funding application. SLR submitted the funding application to the State on May 31. The State informed the Town on July 13, that the project did NOT receive funds. The State received 51 funding applications.
Sinkhole at 57 South Road
Failure of an existing 30-inch CMP drainage pipe caused a very large sink hole. Hinckley Construction was called out to remove and replace the failed line with a new 30-inch HDPE pipe plus 3 new 5-foot drainage MHs. This work has been completed.